Architectural design presentation · R18 · November 2026

A hotel shaped
by the bay.

Wafaiya Yanbu Hotel & Annex
A five-star hospitality proposal for the Red Sea coast.

Explore the design
WafaiyahContractor
Royal CommissionReviewing authority
Yanbu, Saudi ArabiaCoastal hospitality & events
Client & authority presentationDesign development · R18 · 9 November 2026

The design

One destination. Four connected strengths.

The architecture combines the privacy of a retreat with the public life of a hotel and events destination.

02 / 68
The folded hotel wings, landscaped podium and separate annex establish a legible coastal destination.

Rooms directed toward the water

The Z-shaped massing opens different view angles; the sawtooth frontage turns individual window bays toward the bay and sea horizon.

An active waterfront

Dining, terraces, pool and wellness extend the guest experience beyond the room.

An annex with its own identity

A distinct entrance and large halls allow event and recreation uses to operate with greater independence from the hotel.

A coordinated coastal palette

Warm stone, bronze-toned solid aluminium and layered shading connect the exterior to the interior.

Design intent interpreted from the supplied plans, exterior collection and Design Review Checklist. Five-star classification is the project target; approval is not represented as granted.

The design

The bay is the organising idea.

A clear relationship between the urban approach, the landscaped arrival and the Red Sea frontage.

03 / 68
Coastal masterplan visualisation. Context and distances remain subject to the surveyed site model.
Arrival on the land side.
Experience toward the water.

The massing opens a sequence from the arrival courts through the hotel to sea-facing dining, balconies and terraces. The annex holds its own arrival address while the bridge expresses a connected destination.

The bay offers foreground activity; the wider sea horizon gives distance and sunset identity. These are distinct view qualities to record from each key.

Design-review location: 24°00′59.2″ N, 38°09′40.6″ E.
The environmental report uses a different location. Align the survey, true north and Forma model before the next analysis issue.
Sources: Exterior 01; Design Review Checklist, F6. Rendering is a design visualisation, not a surveyed map.

The design

The site model connects land, bay and horizon.

Context evidence supplied by the design team, shown alongside the presentation visualisations.

04 / 68
Design-review workbook: contextual model placed against the surrounding site.
RCJY checklist: supplied site-plan image with the bay edge and urban approach.

Waterfront relationship

The bay defines the principal landscape and guest-experience edge. The building form responds through several frontage orientations.

Urban approach

Read arrivals, annex access and parking against the surrounding streets and public realm.

Common geographic basis

Use the confirmed survey and true north for views, sun, wind and all future contextual renders.

Sources: Design Review Checklist embedded image 01 and RCJY checklist embedded image 08. This is supplied model imagery, not an independently verified land survey.

The design

A repeated fold with a clear purpose.

The Z-shaped building establishes the view opportunities; the sawtooth bay refines the orientation of each room.

05 / 68
Actual guest-floor plan crop: the folded room frontage and connecting corridor.
BAY / SEA HORIZON — CONCEPTUAL VIEW DIRECTIONDiagram of the principle only · no measured azimuth, angle or guaranteed view percentage

Turn the window toward the view

The angled face can direct a room’s primary view obliquely toward the bay, where a straight elevation would look more squarely inland or toward a neighbouring wing.

Use the return for privacy and shade

The return wall and side screen can interrupt direct balcony-to-balcony sightlines. Their height, angle and perforation need checking from both seated and standing eye levels.

Repeat a buildable family

Rationalise the folds, glazing modules, corner details and screen fixings. The value is stronger views and identity with a controlled number of components.

Sources: A-05 PDF / internal drawing A-104; Design Review Checklist F8 and F11. Full sea views are not demonstrated for every room. Original PDF

The design

A view strategy that supports the room offer.

A clear hierarchy of experiences, supported by a room-by-room view schedule in the next design stage.

06 / 68
The private balcony frames the bay in the foreground and the sea beyond.

Design-team view allocation

50% full bay + sea30% partial sea20% horizon

The checklist describes 50% of rooms with full bay and sea views, 30% with approximately 75% sea exposure, and 20% with approximately 50% horizon exposure.

These are design-team allocations, not independently verified visibility measurements. They are not converted into key counts until the room schedule is reconciled.

Validation that protects the value

For each key, record the bed, seating and balcony views; the floor level; adjacent privacy; potential future obstructions; and glare at the intended use time.

Source: Design Review Checklist F7. Visual: Exterior 11. No room revenue or price premium has been calculated.

The design

Two arrivals, one coherent destination.

Separate guest, event and service movements while maintaining an understandable relationship between the buildings.

07 / 68
Ground-floor composition: main hotel to the left, separate annex to the right, and distinct arrival courts.

Hotel guests

Arrival court, concierge, reception and guest lifts create a legible route to the guestrooms.

Events and recreation

The annex lobby provides a separate address. Event visitors can enter without using the main hotel reception sequence.

Service and operations

Basement kitchens, laundry, ramps and service lifts provide the operating backbone. Confirm loading, waste and event set-up routes on a coordinated circulation overlay.

Source: A-02 / internal A-101 and A-01 / internal A-100. Route narrative is a planning interpretation; final accessibility and life-safety routing remains to be verified. Original PDF

The design

The annex broadens the destination.

A flexible activity anchor that can support hotel business and destination use throughout the day.

08 / 68
Revised annex arrival: the central ring waterfall and front planting are retained; the bridge waterfall and plaza fountain jets are removed.
2large hall volumes
2,278 m²combined tagged hall area
323 m²tagged entrance lobby

Large spaces with independent access

The ground plan tags an indoor sports area of 1,143 m² and an indoor gymnasium of 1,135 m², with a central lobby, toilets, stairs and support rooms.

The project brief proposes multipurpose event use. Exhibitions, receptions and community events can complement sports, subject to approved layouts and operational planning.

The supplied Revit labels are sports/gymnasium uses. Event occupancy, seating capacity, fire strategy, acoustics and loading must be coordinated before describing the halls as approved event venues.
Hall and lobby areas are rounded room tags from A-02, not gross building areas. Annex BUA (R18): 8,773 m² – GFA 5,753 m² + basement 3,020 m². R18 annex sheet WFY-AR-108 (PDF)

Project numbers

The project, measured transparently.

Separate the building footprint, the above-ground floor-area reference and the total built-up area.

09 / 68
Level / basisMain hotel m²Annex m²Combined m²
Basement13,842.003,020.0016,862.00
Ground5,568.973,020.008,588.97
Mezzanine2,471.25805.003,276.25
First3,188.64805.003,993.64
Second3,402.75—3,402.75
Third3,402.75—3,402.75
Fourth3,402.75—3,402.75
Fifth3,402.75—3,402.75
Sixth3,402.75—3,402.75
Roof floor1,719.001,123.002,842.00
GFA – excl. basement29,961.615,753.0035,714.61
BUA – incl. basement43,803.618,773.0052,576.61
21,934.89total land m² (Lot 26 + Lot 23)
33.0%hotel site coverage, Lot 26 (5,568.97 / 16,894.98 m²) – annex 59.9%
1.628FAR (GFA ÷ land)

Definitions used in this report

GFA (R18): all floors excluding the basement, including the roof floors: 35,714.61 m² (hotel 29,961.61 + annex 5,753.00).

BUA (R18): all floors including the basement: 52,576.61 m² (hotel 43,803.61 + annex 8,773.00).

Footprint: ground-floor area of 8,588.97 m². Hotel coverage is 32.96% of Lot 26; annex coverage is 59.92% of Lot 23.

Areas from the R18 area schedule on sheet WFY-AR-000 (9 November 2026), checked by the design team. They match the Proposed Facilities of Hotel and Annex – FINAL workbook.
Source: R18 area schedule, WFY-AR-000 (9 November 2026). Land: Lot 26 = 16,894.98 m², Lot 23 = 5,039.91 m².

Project numbers

305 room modules across five guest floors.

Client-confirmed capacity: 61 modules on each of floors 2–6. The table below shows the separate, provisional sellable-key interpretation.

10 / 68
61room modules per guest floor
5guest floors · second through sixth
305total room modules · confirmed by client
Room / key typeFloors 2–4 keysFloors 5–6 keysTotal keys²m² / key¹Total m²¹Key mix²
Presidential suite0222004000.9%
Two-bedroom suite126181202,1607.9%
Executive suite211233802,64014.5%
Typical king573895403,80041.7%
Typical twin422870402,80030.7%
Accessible room6410404004.4%
Total calculated from rows13890228—12,200100%

How modules become keys

The supplied suite mix uses 183 modules on floors 2–4 and 122 modules on floors 5–6: 305 modules in total. Suites combine modules behind one sellable key.

²The provisional suite grouping calculates to 228 keys. The source’s printed 220-key total is arithmetically inconsistent. The 305-module capacity is confirmed; the final sellable-key grouping needs the coordinated room schedule.
Sources: Client correction, 29 September 2026; Screenshot 2026-09-29 172253. ¹Nominal planning areas, not measured room areas or BUA. Module counts do not define bedrooms or licensed occupancy. Accessible provision is listed, not certified compliant.

Guest experience

The view continues inside.

A five-star experience depends on the complete room, from arrival and storage to privacy, sleep quality and outlook.

11 / 68
King room: a calm palette and a clear visual connection to the balcony.
Suite living room: seating and dining arranged around daylight and the coastal outlook.

A consistent interior language

Warm timber, sand-toned stone, bronze accents and restrained teal connect the guestrooms to the public spaces.

Comfort at the window

Coordinate side screens, solar-control glazing, blackout curtains and furniture so the view is comfortable at the time guests use it.

Validate the repeated module

Check furniture clearances, accessible routes, luggage, bathrooms, acoustics and air distribution in a coordinated prototype before repetition.

Sources: Coordinated Interiors V2, King Bedroom 01 and Suite Living Room 01. Image-based concept views; exact geometry and specification require coordination with the Revit model.

Guest experience

A connected offer for meetings and celebrations.

A hierarchy of spaces serves intimate meetings, hotel banquets and larger activities in the annex.

12 / 68
Banquet hall: a generous glazed edge and a clear relationship with prefunction space.
Boardroom: a more intimate setting for business and hosted meetings.

Hotel banquet halls

The ground plan tags Hall 1 at 736 m² and Hall 2 at 637 m². Prefunction, buffet/breakout and preparation areas support the event sequence.

First-floor meeting suite

Seven multipurpose-room tags, smaller meetings, a conference room, breakouts and a prayer room offer several event scales.

Annex event potential

Large annex volumes extend the offer. Coordinate conversion layouts, acoustic separation, AV, rigging, storage and service access for every proposed use.

Sources: A-02 and A-04 room tags; Banquet Hall and Boardroom concept views. Tagged net areas are not seating capacities. Occupancies and exits require approved event configurations.

Guest experience

Wellness and outdoor life form one sequence.

The hotel’s leisure value comes from the relationship between indoor wellness and the landscaped coast-facing spaces.

13 / 68
Spa reception: a quieter material and lighting expression within the same design family.
Pool terrace: the coastal outlook becomes a shared amenity.

Mezzanine wellness

The Revit plan includes men’s and women’s gyms, spas, massage rooms, saunas, steam rooms and Moroccan baths.

Comfort at the edge

Provide shaded resting areas and tested wind shelter. Keep the central outlook open while treating exposed returns and corners.

Operational separation

Coordinate wet and dry routes, privacy, changing facilities, drainage, pool servicing and staff access with the operator.

Sources: A-03 / A-102; Spa Reception 01; Exterior 09. Pool and outdoor images are concept visualisations.

Guest experience

A roof destination with an environmental response.

The environmental study identifies the exposed roof as the priority for further design testing.

14 / 68
Roof restaurant: indoor dining connects to the terrace and sea horizon.
504 m²tagged indoor roof restaurant
577 m²tagged business lounge
69 m²tagged restaurant preparation

The roof combines hospitality uses with a strong coastal outlook. Its viability depends on a comfortable outdoor edge, service access and space for the building systems.

Design the shade and wind screen together

Place long-stay seating behind a tested screen line and provide overhead shade with supplementary protection from low western sun.

Coordinate the whole roof

Reserve plant, maintenance, drainage, PV, access and fire routes before the restaurant and terrace boundaries are fixed.

Source: A-10 / internal A-109 room tags and supplied Forma report. Screen dimensions, wind performance and PV capacity are not final designs.

Climate response

Keep the sheltered podium. Improve the exposed roof.

Use wind analysis to place activities and refine the building’s outdoor rooms.

15 / 68
Supplied Forma wind-comfort plan. The podium reads as a sheltered pocket; the upper roof zones read as exposed.

What the supplied study reports

Seventeen wind cases examine the whole rose and individual directions at 1.75 m above selected surfaces. The reported ground-level aggregate contains no “uncomfortable” area, but a substantial share is suited to walking rather than sitting.

Design response: locate longer-stay seating in sheltered zones; test the roof edges, corners, entrances and terrace openings individually. A site-wide percentage does not establish dining comfort at every point.

Retain the qualitative sheltered-versus-exposed finding. Re-run the model at the confirmed site coordinates, with the current geometry and stated weather input, before fixing screen geometry.
Reported caseScaleSit / standStroll / walkUncomfortable
Whole rose, aerialNEN 810022%77%0%
Whole rose, planNEN 810021%79%0%
NW 315°NEN 810022%77%0%
Whole rose, siteLawson LDDC6%93%0%
Whole rose, obliqueLawson LDDC5%95%0%
Source: Environmental Analysis, 19 September 2026, Study 03. Percentages are rounded source values and may not sum to 100%. Method reference: Autodesk Forma wind analysis. This presentation does not certify outdoor comfort.

Climate response

Moderate the wind while keeping the view open.

The architectural aim is a comfortable occupied zone with a usable sea outlook.

16 / 68

Roof venue

Test porous or operable screens along exposed edges. Set dining inboard of the parapet, and compare several screen options in the model.

Pool and dining terraces

Use planted shelter at exposed returns and upwind ends. Assess the sitting zone rather than relying on a general walking-comfort result.

Structure and maintenance

Screens, planters and shade structures all require wind-load design, secure fixings and maintainable coastal finishes. Planting on slabs is part of the structural coordination.

The source proposes 40–50% screen porosity and heights of 1.8–2.1 m. Treat these as options to test, not approved dimensions or guaranteed comfort improvements.
Sources: supplied Forma figures and recommendations; Exterior 14. Additional technical checks are design recommendations, not completed engineering results.

Climate response

Shade the occupied areas. Reserve the solar opportunity.

The same solar exposure that creates shading demand also creates an opportunity for integrated generation.

17 / 68
Sun-hours output: exposed ground and roof surfaces receive long periods of direct sun in the supplied June run.
Solar/PV output: selected model surfaces and an indicative energy estimate.
10,409 m²source solar-selection surface, 0–75°
20.9 GWh/yrsource incident solar energy
1.52 GWh/yrsource indicative PV yield

A design input, not an energy guarantee

The report quotes approximately 6,246 m² of panels at 60% coverage and 15% efficiency. The selected surface includes model geometry; it is not a confirmed installable roof array.

Next coordinated step

Reconcile the analysis location, usable roof and canopy areas, plant clearances, structure, maintenance, shading, module data and system losses. Confirm a new annual yield before investment decisions.

Source values: Environmental Analysis, Study 04. Incident energy and electrical yield are different quantities. The source’s higher-efficiency scaling is an arithmetic scenario, not an independently simulated or bankable yield.

Climate response

Read the shadow through the day and the seasons.

The supplied frames show how the massing redistributes shade; afternoon use areas need deliberate landscape and facade protection.

18 / 68
Source: Environmental Analysis, Study 02. Times and dates reproduced as labelled in that report. Model coordinates and clock settings require alignment with the confirmed site before detailed shade sizing.

Climate response

Protect the outlook from heat and glare.

The facade should vary where orientation and exposure vary, while maintaining one architectural language.

19 / 68
Supplied daylight-potential view. Recessed faces and balcony returns require room-level investigation.

High sun: horizontal shade

Balconies, canopies and roof pergolas can intercept higher-angle sun. Size them for the actual facade azimuth and occupation hours.

Low western sun: side protection

Use the sawtooth returns, vertical fins and adjustable or perforated screens to address low-angle exposure while preserving selected view corridors.

Room comfort: a complete system

Coordinate glazing, opening area, curtains and internal blinds with energy, daylight and glare models. Compare wing-specific facade options using the same room and HVAC assumptions.

A view is not evidence of daylight or thermal compliance. No annual room-level glare results, final glazing values, cooling-load comparison or verified U-values were supplied.
Sources: Design Review Checklist items 4–6; Environmental Analysis, Studies 01–02. Autodesk analysis guidance.

Landscape

A coastal landscape carried above the basement.

A low, coastal planting character reinforces the architecture while framing water, shade and movement.

20 / 68
Supplied coloured landscape plan and plant legend. All planting fill is slab-supported; trees and palms require engineered pockets.

Keep the waterfront legible

Use lower planting in primary view corridors and locate taller elements to frame arrivals, edges and sheltered seating.

Treat the roof of the basement as a system

Coordinate saturated planting loads, root anchorage, soil volumes, waterproofing, root barriers, drainage, overflow and inspection access.

Design for salt and water use

Group plants by irrigation demand and exposure. Test irrigation-water and soil salinity; provide drainage and a maintenance plan.

Source: 01_Coloured_Landscape_Plan.jpg, issued 29 September 2026. Concept only; planting extents and quantities are not measured in this presentation.

Landscape

Select for coastal ecology, then verify the planting system.

The supplied palette is a strong starting point for Yanbu’s salt exposure, dry conditions and open sea views.

21 / 68
Plan codePlantPresentation roleCoordination requirement
P01Arak / miswakSalvadora persicaPrimary small-tree candidateEngineered pockets; confirm canopy, salinity and supply.
P02Samr / umbrella thornVachellia tortilisReserve shade-tree optionKeep thorns away from guest paths; confirm root volume and exposure.
P03Doum palmHyphaene thebaicaReserve accent palmAllow mature crown, weight and anchorage; engineered pockets only.
P04Coastal saltbushSuaeda vermiculataCoastal shrub / coverUse for exposed mineral beds; verify nursery provenance.
P05Succulent saltbushTetraena coccineaLow coastal massingConfirm identity; regional literature also uses Zygophyllum coccineum.
P06Coastal sea lavenderLimonium axillareFlowering coastal edgeTrial in the specified substrate and irrigation regime.
P07Thumam grassPanicum turgidumDry, sheltered mineral bedsKeep clear of routes and services; confirm mature spread.
P08Creeping saltgrassAeluropus lagopoidesLow saline-tolerant coverDefine edges and maintenance; keep drains inspectable.
P09Silvery groundcoverCressa creticaLow coastal coverUseful where long sea sightlines must remain open.
P10–P12Client reference palm, tree and clipped shrubVisual references onlySpecies, native status and mature size remain unconfirmed.
Recommended base: the supplied low coastal shrubs, grasses and groundcovers. Retain trees/palms only where structural pockets and mature clearances work. P02/P03 remain reserve options; do not procure P10–P12 from visual references alone.
Source: supplied landscape legend. Regional support: Flora of Saudi Arabia — Northern Tihama and Sabkhas. Regional occurrence supports the palette; suitability on this slab requires horticultural and structural approval.

Materials

Warm stone at the arrival.

The supplied boards connect material character, facade use and coastal durability.

22 / 68
Exterior material board 01 — Main entrance.
Source: Yanbu_Hotel_Two_Material_Boards.pdf, board 1. Materials are proposed concept specifications. Product approvals, fire performance and supplier environmental documents remain to be coordinated.

Materials

A durable palette along the sea frontage.

The supplied boards connect material character, facade use and coastal durability.

23 / 68
Exterior material board 02 — Sea-front facade.
Source: Yanbu_Hotel_Two_Material_Boards.pdf, board 2. Materials are proposed concept specifications. Product approvals, fire performance and supplier environmental documents remain to be coordinated.

Materials

Solid aluminium gives the bronze language precision.

A shared material and pattern vocabulary connects the facade with the public interiors.

24 / 68
Arrival facade: stone surfaces and bronze-toned metalwork establish a consistent detail family.

Exterior cladding and screens

Use solid aluminium panels for the selected metal-clad zones, soffits and laser-cut decorative screens. Coordinate panel thickness, stiffeners, joints and replaceable fixings with the facade engineer.

Interior continuity

Repeat the bronze tone and selected pattern in lobby screens, feature panels and ceiling accents. If a perforated panel is intended to absorb sound, coordinate the tested acoustic backing and cavity.

Coastal finish

Specify verified pretreatment, finish class, fabrication quality and a coastal warranty. Laser-cut and deburr before finishing; protect cut edges and isolate incompatible metals.

The supplied boards identify Riyadh limestone, insulated double walls, aluminium screens, low-E glazing, laminated balustrades, marine stainless steel, paving, porcelain and GRC. Solid aluminium cladding is the current client direction for selected metal zones; its exact elevation extent must be mapped.
Sources: material boards and client brief. Finish reference: QUALICOAT Seaside. A coating class or solid metal face alone does not establish full facade fire compliance or LEED certification.

Materials

A layered external wall for a coastal hotel.

The two masonry leaves provide the enclosure; continuous insulation, controlled air leakage and a drained outer finish complete the performance strategy.

25 / 68
01 · Inner finishRoom-side finish and sealed penetrations.
02 · Inner masonry leafRobust room enclosure and acoustic mass.
03 · Outer masonry leafTied, coordinated backing construction.
04 · Air / water controlContinuous layer with sealed interfaces.
05 · Mineral-wool insulationContinuous thermal layer; minimise bridges.
06 · Drained cavityDrainage, flashings and cavity barriers.
07 · External finishMechanically fixed stone or solid aluminium at selected zones.

Thermal continuity

Carry insulation past columns and slab edges. Check balcony connections, metal brackets, window perimeters and roof junctions as thermal bridges.

Moisture and durability

Provide drained and inspectable interfaces. Select the air/vapour-control strategy from a project-specific condensation assessment for air-conditioned coastal conditions.

Fire, sound and maintenance

Engineer ties, supports, cavity fire barriers and movement joints. Verify acoustic and fire performance of the complete assembly and provide access to replace facade components.

Concept sequence derived from Board M02; not a construction detail and not to scale. Final leaf spacing, layer order, insulation thickness and fixings require facade, structural, fire and MEP coordination. No calculated wall U-value is claimed.
Source: Material Boards M01/M02. Regulatory reference: Saudi Building Code system. The applicable permit edition and project criteria must be confirmed.

Materials

Turn sustainability intent into documented performance.

The presentation connects the design intent with the evidence needed to substantiate it.

26 / 68
StrategyEvidence to carry into procurementDecision basis
Solid aluminiumVerified recycled content; product EPD where available; finish and sourcing records.Match the selected LEED version and credit criteria.
Stone, porcelain and other finishesProduct-specific environmental information and durable, repairable installation.Do not infer environmental performance from material name alone.
Paints, adhesives, sealants and interiorsVOC content/emissions evidence where required; ingredient disclosures where applicable.Review wet-applied products and composite assemblies individually.
Envelope, roof and glazingEnergy model, assemblies, glazing properties, thermal bridges and commissioning.Savings need a model and baseline; no percentage is claimed here.
Landscape and waterPlanting/irrigation schedule, water demand and water-quality data.Native or regional planting does not by itself prove water savings.
PV and operationCoordinated array, annual yield model, metering and maintenance plan.Source Forma estimate is preliminary.

LEED compliance intent

The project brief calls for LEED-compliant material selection. Use a materials register linking every specified product to the relevant evidence and the project’s selected LEED rating system.

A durable coastal asset

Prioritise replaceable panels, maintainable coatings, accessible drainage and robust interfaces. Whole-life value depends on preserving performance under salt, humidity and UV exposure.

LEED certifies projects, not individual products. The supplied files do not establish a registered LEED version, awarded credits or certification level. Present this as a LEED-supporting specification strategy until those records are confirmed.
Reference: USGBC — product contribution to LEED. Recommendations are a documentation pathway, not an assessment of credit achievement.

Plans & architecture

A clear hierarchy from operations to the roof.

Programme distribution helps explain the building before the detailed drawings are reviewed.

27 / 68
RoofRestaurant, business lounge and outdoor venues+32.00 m
Floors 2–661 room modules per floor · 305 total+12–28 m
FirstMeetings, multipurpose rooms and support+8.00 m
MezzanineWellness, gyms, spas and administration+4.50 m
GroundArrival, banquet, dining, retail and annex halls±0.00 m
BasementParking, kitchen, laundry, MEP and security−4.50 m
Public life below.
Guest privacy above.
Operations connected.

The public floors form the hotel’s social and event base. Five guest floors share the repeated room-module system. The roof adds a destination venue, while the basement supports the hotel’s daily operation.

Levels shown relative to ground, derived from A-13: ground is −12.00 m in the source’s model datum; roof deck is +20.00 m, giving 32.00 m above ground. The labelled apex is 36.00 m above ground. This is not a certified statutory height calculation.

The following pages move through every supplied floor plan, then the elevations and sections.

Sources: A-01–A-10 and A-13. Structural BOQ levels use a different datum and heights; coordinate before tender.

Plans & architecture

Basement — the operating backbone.

Hotel 13,842.00 m² · Annex 3,020.00 m² (R18)

28 / 68
WFY-AR-101 · R18 (9 Nov 2026) — enlarge to inspect the full sheet, furniture and space schedule.

Core functions

Parking (266 hotel + 102 annex bays incl. EV charging and EV-ready), main kitchen and food support 753.5 m², laundry 680 m², security, staff lockers, MEP and water tanks.

Operational benefit

Concentrates support functions beneath the guest-facing programme and links them vertically through service cores.

Coordination

Verify parking totals, accessible bays, loading/receiving, waste flow, ventilation, compartmentation and ramp geometry.

Source: R18 sheet WFY-AR-101 (9 November 2026). Areas from the R18 area schedule and the verified space program (FINAL).

Plans & architecture

Ground floor — arrivals, dining and large halls.

Hotel 5,568.97 m² · Annex 3,020.00 m² (R18)

29 / 68
WFY-AR-102 · R18 (9 Nov 2026) — enlarge to inspect the full sheet, furniture and space schedule.

Main hotel

Concierge, reception, cafe, banquet halls, all-day dining, preparation and support.

Outdoor connections

Pool, family-resort area, alfresco dining, walkways and landscaped edges extend the public rooms.

Separate annex

Two large sports/gymnasium-tagged halls flank the annex entrance lobby. Event adaptation is subject to coordination.

Source: R18 sheet WFY-AR-102 (9 November 2026). Areas from the R18 area schedule and the verified space program (FINAL).

Plans & architecture

Mezzanine — wellness and administration.

Hotel 2,471.25 m² · Annex 805.00 m² (R18)

30 / 68
WFY-AR-103 · R18 (9 Nov 2026) — enlarge to inspect the full sheet, furniture and space schedule.

Wellness programme

Men’s gym 289.59 m²; women’s gym 291 m²; men’s spa 355 m²; women’s spa 355 m² (treatment rooms, sauna, steam, Moroccan bath); admin office 111 m².

Spatial relationship

Double-height voids retain the scale of the public rooms below.

Coordination

Separate wet and dry circulation, coordinate privacy and access, and exclude open-to-below zones from area totals as applicable.

Source: R18 sheet WFY-AR-103 (9 November 2026). Areas from the R18 area schedule and the verified space program (FINAL).

Plans & architecture

First floor — meetings and multipurpose rooms.

Hotel 3,188.64 m² · Annex 805.00 m² (R18)

31 / 68
WFY-AR-104 · R18 (9 Nov 2026) — enlarge to inspect the full sheet, furniture and space schedule.

Flexible rooms

Six expandable multipurpose halls totalling 1,350 m², plus 3 small meeting rooms (108 m²) and 4 break rooms (258 m²).

Support spaces

Conference, small meeting and breakout rooms, prayer room, housekeeping and linen support.

Area reconciliation

R18 confirms 3,188.64 m² for the main hotel first floor; outdoor decks and landscaping (2,944 m²) are open and not counted in GFA.

Source: R18 sheet WFY-AR-104 (9 November 2026). Areas from the R18 area schedule and the verified space program (FINAL).

Plans & architecture

Second floor — 61 room modules.

3,402.75 m² hotel (R18) · 61 modules

32 / 68
WFY-AR-105 · R18 (9 Nov 2026) — enlarge to inspect the full sheet, furniture and space schedule.

Guest-floor structure

Folded perimeter bays are served by a connected corridor and two principal guest-lift zones.

Support on the floor

Housekeeping, linen, service circulation, shafts and escape stairs are retained within the plan.

Key grouping

The supplied floors 2–4 suite mix implies 46 keys per floor if distributed equally. This is a provisional grouping of 61 modules.

Source: R18 sheet WFY-AR-105 (9 November 2026). Areas from the R18 area schedule and the verified space program (FINAL).

Plans & architecture

Third floor — the repeated guest module.

3,402.75 m² hotel (R18) · 61 modules

33 / 68
WFY-AR-105 · R18 (9 Nov 2026) — enlarge to inspect the full sheet, furniture and space schedule.

Repeat with control

Carry the same room-module geometry, core logic and coordinated facade family through the guest levels.

View assessment

Record the view from each actual key at this elevation, including the balcony returns and neighbouring wings.

Key grouping

Floors 2–4 form a 183-module group. Final key IDs and suite boundaries must be reconciled with the 138-key arithmetic from the source mix.

Source: R18 sheet WFY-AR-105 (9 November 2026). Areas from the R18 area schedule and the verified space program (FINAL).

Plans & architecture

Fourth floor — continuity of the guest floors.

3,402.75 m² hotel (R18) · 61 modules

34 / 68
WFY-AR-105 · R18 (9 Nov 2026) — enlarge to inspect the full sheet, furniture and space schedule.

Design continuity

The folded facade remains the organising rhythm for rooms, windows, balconies and shading.

Guest comfort

Check privacy, glare and daylight by orientation; do not infer performance solely from the repeated plan.

Model issue

The client confirms 61 modules per floor. Clean and reconcile room tags and schedules before the statutory issue.

Source: R18 sheet WFY-AR-105 (9 November 2026). Areas from the R18 area schedule and the verified space program (FINAL).

Plans & architecture

Fifth floor — the upper suite offer.

3,402.75 m² hotel (R18) · 61 modules

35 / 68
WFY-AR-106 · R18 (9 Nov 2026) — enlarge to inspect the full sheet, furniture and space schedule.

Upper-floor mix

The source introduces presidential suites within the combined floors 5–6 matrix.

Module-to-key logic

122 modules across the two upper guest floors can form the listed 90-key provisional mix; this averages 45 keys per floor.

Validation

Map each suite to real module IDs and confirm connecting arrangements, fire separation, services and views.

Source: R18 sheet WFY-AR-106 (9 November 2026). Areas from the R18 area schedule and the verified space program (FINAL).

Plans & architecture

Sixth floor — the highest guestroom level.

3,402.75 m² hotel (R18) · 61 modules

36 / 68
WFY-AR-106 · R18 (9 Nov 2026) — enlarge to inspect the full sheet, furniture and space schedule.

Coastal outlook

The elevation offers a different horizon relationship; views remain subject to the actual room position and surrounding context.

Upper-floor coordination

Review roof acoustics, waterproofing, mechanical plant and service routing above guestrooms.

Capacity

The second through sixth floors total 5 × 61 = 305 room modules. This is the confirmed planning capacity.

Source: R18 sheet WFY-AR-106 (9 November 2026). Areas from the R18 area schedule and the verified space program (FINAL).

Plans & architecture

Roof deck — hospitality, shelter and services.

Hotel 1,719.00 m² · Annex 1,123.00 m² (R18)

37 / 68
WFY-AR-107 · R18 (9 Nov 2026) — enlarge to inspect the full sheet, furniture and space schedule.

Hospitality

Indoor restaurant, business lounge, preparation, outdoor restaurant/deck and cafe areas.

Environmental priority

Coordinate wind screens, overhead shade, low-sun protection and inboard seating with the latest Forma model.

Area and services

R18: hotel roof 1,719 m², annex roof 1,123 m². The upper roofs carry the solar PV arrays and the screened MEP plant zone behind a high parapet.

Source: R18 sheet WFY-AR-107 (9 November 2026). Areas from the R18 area schedule and the verified space program (FINAL).

Plans & architecture

Front and rear elevations.

Read the facade rhythm, podium, guest floors and roof treatment as one composition.

38 / 68
WFY-AR-130 · R18 — Exterior Elevations Front And Rear. Enlarge for the full sheet.
Source: R18 sheet WFY-AR-130 (9 November 2026). Heights and interfaces require coordinated architectural/structural sign-off.

Plans & architecture

Left and right elevations.

The return elevations explain the relationship between folded bays, solid walls and the site.

39 / 68
WFY-AR-131 · R18 — Exterior Elevations Left And Right. Enlarge for the full sheet.
Source: R18 sheet WFY-AR-131 (9 November 2026). Heights and interfaces require coordinated architectural/structural sign-off.

Plans & architecture

Sections reveal the spatial hierarchy.

Public-room heights, vertical circulation and the guest-floor stack connect the design intent to the building section.

40 / 68
WFY-AR-132 · R18 — Building Sections. Enlarge for the full sheet.
Source: R18 sheet WFY-AR-132 (9 November 2026). Heights and interfaces require coordinated architectural/structural sign-off.

Exterior collection · R18

Latest views – roof PV and parapet.

The current 3D: solar PV arrays on the upper roofs and the annex roof, concealed behind a high stone parapet.

45 / 68
Renders consistent with the latest 3D model and project film (November 2026).

Films & downloads

Films and R18 downloads.

The project films and the current R18 / FINAL documents.

46 / 68
Hotel experience film · the guest journey
Royal Commission architectural film · as submitted

Downloads – R18 (9 November 2026)

All documents are the R18 / FINAL issue; earlier figures in this presentation are superseded where they differ. Main project site: wafaiyahotel5star.d57.space

Interior collection

Main lobby and reception & lobby cafe.

Coordinated interiors · spaces 1–2 of 22 · two views of each space

47 / 68
Sources: supplied Coordinated Interiors V2 and the 44 named image files. These are image-based concept views. Validate exact dimensions, hidden geometry and pattern alignment in the coordinated 3D model.

Interior collection

All-day dining & business lounge.

Coordinated interiors · spaces 3–4 of 22 · two views of each space

48 / 68
Sources: supplied Coordinated Interiors V2 and the 44 named image files. These are image-based concept views. Validate exact dimensions, hidden geometry and pattern alignment in the coordinated 3D model.

Interior collection

Banquet hall & conference room.

Coordinated interiors · spaces 5–6 of 22 · two views of each space

49 / 68
Sources: supplied Coordinated Interiors V2 and the 44 named image files. These are image-based concept views. Validate exact dimensions, hidden geometry and pattern alignment in the coordinated 3D model.

Interior collection

Corner meeting room & breakout meeting room.

Coordinated interiors · spaces 7–8 of 22 · two views of each space

50 / 68
Sources: supplied Coordinated Interiors V2 and the 44 named image files. These are image-based concept views. Validate exact dimensions, hidden geometry and pattern alignment in the coordinated 3D model.

Interior collection

Boardroom & fitness centre.

Coordinated interiors · spaces 9–10 of 22 · two views of each space

51 / 68
Sources: supplied Coordinated Interiors V2 and the 44 named image files. These are image-based concept views. Validate exact dimensions, hidden geometry and pattern alignment in the coordinated 3D model.

Interior collection

Basketball court & spa reception.

Coordinated interiors · spaces 11–12 of 22 · two views of each space

52 / 68
Sources: supplied Coordinated Interiors V2 and the 44 named image files. These are image-based concept views. Validate exact dimensions, hidden geometry and pattern alignment in the coordinated 3D model.

Interior collection

Spa treatment room & moroccan bath.

Coordinated interiors · spaces 13–14 of 22 · two views of each space

53 / 68
Sources: supplied Coordinated Interiors V2 and the 44 named image files. These are image-based concept views. Validate exact dimensions, hidden geometry and pattern alignment in the coordinated 3D model.

Interior collection

Guest corridor & lift lobby.

Coordinated interiors · spaces 15–16 of 22 · two views of each space

54 / 68
Sources: supplied Coordinated Interiors V2 and the 44 named image files. These are image-based concept views. Validate exact dimensions, hidden geometry and pattern alignment in the coordinated 3D model.

Interior collection

King bedroom & twin bedroom.

Coordinated interiors · spaces 17–18 of 22 · two views of each space

55 / 68
Sources: supplied Coordinated Interiors V2 and the 44 named image files. These are image-based concept views. Validate exact dimensions, hidden geometry and pattern alignment in the coordinated 3D model.

Interior collection

Suite living room & suite dining room.

Coordinated interiors · spaces 19–20 of 22 · two views of each space

56 / 68
Sources: supplied Coordinated Interiors V2 and the 44 named image files. These are image-based concept views. Validate exact dimensions, hidden geometry and pattern alignment in the coordinated 3D model.

Interior collection

Suite office & roof restaurant.

Coordinated interiors · spaces 21–22 of 22 · two views of each space

57 / 68
Sources: supplied Coordinated Interiors V2 and the 44 named image files. These are image-based concept views. Validate exact dimensions, hidden geometry and pattern alignment in the coordinated 3D model.

Submission & evidence

Coordinate the systems that make the hotel work.

Keep the technical commitments visible and connect each to the drawing or schedule that will close it.

58 / 68
WorkstreamEvidence availableNext coordinated deliverable
HVAC and plantArchitectural shafts and some service spaces are shown.Issue system selection, plant layout, intake/exhaust routes, acoustic treatment and maintainable architectural screening.
Electrical infrastructureElectrical-room and shaft tags appear in the architectural plans.Confirm transformer/substation location, utility access, ventilation and coordinated approvals.
Fire and emergency accessEscape stairs and fire-exit labels are shown.Complete occupancy, travel-distance, stair/exit capacity, fire access, hydrant and fire-water layouts.
Waste, loading and kitchensBasement kitchen, laundry, support and waste-chute tags are shown.Confirm collection/holding rooms, loading route, clean/dirty separation and event servicing.
Accessibility and liftsLifts and accessible room quantities appear in the project information.Complete step-free routes, accessible parking/toilets/rooms, door clearances and lift-traffic analysis.
Guestroom and public-space fit-outConcept interiors and room/floor finish schedules are supplied.Resolve unplaced/redundant room entries and complete performance specifications, finishes and coordinated room data.
The architectural presentation supports design review. It does not replace the detailed MEP, fire, accessibility, structural or hotel-classification submissions.
Sources: supplied Revit plan tags and RCJY checklist items 21–26. No approved MEP package, code-compliance report or Ministry classification decision was supplied.

Submission & evidence

RCJY requirements — design and drawings.

Cross-reference to the 27 items in the supplied RCJY presentation checklist.

59 / 68
ItemRequirement / evidence linkPresentation coverageRemaining evidence
01Project identityShown / confirmProject and location included; confirm legal owner, plot details and design-office identity.
02Comparable-project identityConditionalChecklist reference imagery is included; project names, source attributions and relevance need confirmation.
03Areas and functionsShown / reconcileFloor tabulation, area definitions and programme included; signed area plans required.
04Architectural / visual identityShown / developWarm stone, bronze screens and repeated folds explained; confirm RCJY identity acceptance.
05Concept to final solutionShownZ-shaped massing and sawtooth room frontage linked to views and privacy intent.
06Urban contextShown / verifySupplied contextual views included; align verified survey and neighbouring development.
07Circulation and functionsShown / developArrivals, annex and service logic explained; coordinated movement overlay still required.
08Sun and wind studiesShown / reconcileForma evidence included; location, true north and analysis settings must be aligned.
09Sustainability and energyShown / developEnvelope, materials, water and PV strategy presented; quantified evidence pending.
10Site access, parking, servicesShown / verifyGround and basement plans included; parking and service locations need reconciliation.
11Open-space layoutsShownColoured landscape plan, outdoor connections and planting concept included.
12All floor plans, uses and areasShown / reconcileTen floor-plan sheets included, with area basis and coordination notes.
13Vertical sectionsShownBoth building sections included; datum and structural levels need coordination.
Source: RCJY_Presentation_Requirements_Compliance_Checklist.xlsx, rows 7–33. “Shown” refers to content in this presentation, not authority approval. The original workbook’s compliance cells are blank.

Submission & evidence

RCJY requirements — visuals, systems and delivery.

Cross-reference to the 27 items in the supplied RCJY presentation checklist.

60 / 68
ItemRequirement / evidence linkPresentation coverageRemaining evidence
14Exterior daytime viewsShownAll supplied day views included.
15Exterior night viewsShownEvening waterfront and illuminated arrival views included.
16Main interior perspectivesShown44 supplied views across 22 interior spaces included.
17Openings, shading, canopiesShown / developFacade and roof shading strategy explained; detail calculations pending.
18Exterior and interior materialsShown / developExterior boards and interior palette included; final product register pending.
19Colours and identityShownStone, bronze, warm timber and restrained teal linked across spaces.
20Samples / material boardsShownBoth original material boards included; physical samples remain a later deliverable.
21HVAC and unit locationsRequiredNo coordinated HVAC system/plant-location drawing supplied.
22Architectural AC screeningRequiredProvide screened plant elevations, ventilation and maintenance clearances.
23Transformer locationsRequiredConfirm utility-approved transformer/substation layout.
24Waste-container locationsRequiredIssue collection, holding and vehicle-access layout.
25Fire hydrantsRequiredIssue coordinated hydrant, fire-water and emergency-access plan.
26Code and RCJY complianceRequiredProvide signed discipline compliance, accessibility and life-safety evidence.
27Post-approval programmeProposedIndicative sequence supplied for discussion; agreed programme and approvals pending.
Source: RCJY_Presentation_Requirements_Compliance_Checklist.xlsx, rows 7–33. “Shown” refers to content in this presentation, not authority approval. The original workbook’s compliance cells are blank.

Submission & evidence

Carry the review comments into design development.

A concise close-out path keeps the concept’s strengths intact as the information becomes more detailed.

61 / 68
Checklist itemTeam response recordedEvidence still to complete
1 · Base model / contextTeam records verified Google Earth location and true north.Align survey and Forma coordinates; keep one controlled site model.
2 · Sea-view matrixTeam provides 50/30/20 view allocation.Issue key-by-key views from bed, seating and balcony, with privacy tests.
3 · Massing comparisonTeam explains twin tower, U-form, single tower and Z-form reasoning.Record comparable yield, facade cost, solar exposure and buildability evidence.
4–6 · Sun, facade and WWRTeam records ongoing BIM study and a full glazed folded face.Complete annual glare, energy and wing-specific WWR comparisons.
7 · Guestroom validationMarked “Yes started”; interior design stage noted.Coordinate prototype king, twin, accessible and complex corner rooms.
8–9 · Operations, lifts and life safetyPlanning described as substantially developed.Issue operator-reviewed BOH routes, lift study and code/egress analysis.
10 · Waterfront experienceIntegrated in the design and 3D views.Retain the sequence while validating shade, wind and accessible movement.
11–12 · Coastal facade and windBoards and design consideration recorded.Complete specifications and tested wind-mitigation details.
13 · Constructability / valueArchitectural signature is identified as a priority.Rationalise folds and components; test the added cost against the room offer.
The source workbook reports “Completed: 12 / 13”, but several remarks describe future work. This page retains the team responses while distinguishing them from completed technical evidence.
Source: Yanbu_Hotel_Design_Review_Checklist_v2_1.xlsx, Design Review Checklist, rows 6–18. Source completion labels were not treated as independent proof of approval or performance.

Submission & evidence

A staged route from concept to a coordinated hotel.

A clear decision sequence lets the client and reviewing authorities understand what is resolved and what comes next.

62 / 68
01

Resolve the common basis

Agree site coordinates, true north, floor areas, 305-module schedule, suite groupings, operator brief and annex uses.

Indicative coordination allowance: 4–6 weeks.

02

Develop and review

Complete the architectural/MEP/fire interfaces, rooms, facade options, wind mitigation and authority review package.

Indicative design/tender allowance: 12–16 weeks; authority review duration to be agreed.

03

Procure and prototype

Confirm product evidence, facade and guestroom mock-ups, long-lead items, contractor method and coastal maintenance requirements.

Indicative procurement allowance: 10–16 weeks; some work may overlap design.

04

Build, test and commission

Execute the agreed package, test the systems, train operations and complete the required licensing/classification processes.

Initial discussion allowance: 18–24 months; contractor to establish the programme.

These durations are proposed planning allowances, not an approved programme or completion commitment. Validate against scope, approvals, procurement, contractor resources and the operator’s opening requirements.

Client decision

Endorse the view-led massing, the 305-module planning capacity, the hotel/annex relationship and the coordinated material direction.

Technical close-out

Agree one reconciled area and key schedule, then close the environmental, life-safety, accessibility and building-system evidence.

Submission package

Issue controlled drawings and schedules with a revision register and signed discipline responsibilities.

Proposed for discussion in response to RCJY checklist item 27. Ministry of Tourism classification reference: published hotel classification checklist; confirm the criteria applicable at submission. No classification decision is implied.

Submission & evidence

One project needs one controlled set of numbers.

Reconciliation register for the design team. It keeps the persuasive narrative tied to a traceable evidence base.

63 / 68
TopicSource differencePresentation treatment / next action
Room capacityClient confirms 61 modules × 5 guest floors = 305 modules.Use 305 modules throughout; map the suite groupings to real room/key IDs.
Sellable keysMatrix row quantities total 228 keys; printed subtotals total 220.Treat 228 as the provisional grouping calculation. The environmental report’s 258-key / 300-room header is an older conflicting reference.
Main first-floor areaResolved in R18: 3,188.64 m².Closed – R18 area schedule governs.
Main roof-floor areaResolved in R18: 1,719 m².Closed – R18 area schedule governs.
Annex roof-floor areaResolved in R18: 1,123 m².Closed – R18 area schedule governs.
Combined BUA / GFAR18: BUA 52,576.61 m²; GFA 35,714.61 m² (basement hotel 13,842 + annex 3,020).Closed – use R18 / FINAL figures only.
Site coordinatesChecklist: 24.016444° N, 38.161278° E; environmental report: 24.0895° N, 38.0618° E.Resolve location difference before a new Forma issue or detailed solar sizing.
Height / datumA-13 gives roof deck 32 m and apex 36 m above its ground level; environmental text mentions 34 m.Reconcile architectural and structural datums and the height used for each analysis.
Parking and room tagsOlder BOQ records conflicting parking counts; Revit schedules include unplaced/redundant room entries.Issue cleaned schedules from the coordinated model. Do not use room-object counts as sellable keys.
Sources: client correction; supplied screenshots; ARCHITECTURAL_HOTEL_BOQ.xlsx, I_LevelSummary and Levels; Revit sheets; environmental HTML; design-review workbook. Presentation arithmetic does not overwrite the source files.

Source library

The R18 drawing library.

All 16 sheets of the R18 architectural set (9 November 2026), each as its own PDF, plus the earlier solar, structural and schedule studies.

64 / 68
30 sheets

WFY-AR-000 · Cover, drawing list and area schedule

Open R18 PDF

WFY-AR-100 · Site development and landscape plan

Open R18 PDF

WFY-AR-110 · Typical guestrooms – King and Twin

Open R18 PDF

WFY-AR-120 · Interior finishes – material board

Open R18 PDF

WFY-AR-130 · Exterior elevations – front and rear

Open R18 PDF

WFY-AR-131 · Exterior elevations – left and right

Open R18 PDF

Supporting studies – earlier issue (September 2026, no R18 equivalent)

Source: R18 architectural and furniture layout set, sheets WFY-AR-000 to 133 (9 November 2026). Earlier studies are kept for reference only.

Source library

The supplied environmental evidence.

All 21 embedded figures from the supplied environmental report are retained for inspection.

65 / 68
The original report describes 31 runs/frames but contains 21 embedded figures. Its original text is preserved as an archive; the presentation’s reconciliation notes govern how its figures are used.

Source library

Visual references embedded in the RCJY checklist.

34 embedded images retained from the supplied workbook, including contextual views and design references.

66 / 68
Source: RCJY_Presentation_Requirements_Compliance_Checklist.xlsx. Anchors identify the top-left Excel cell of each image. Images may span adjacent rows. Reference-project identities and original attributions were not supplied; these images are not presented as verified built works of the project team.

Source library

Visual evidence embedded in the design review.

17 embedded images retained from the supplied workbook, including contextual views and design references.

67 / 68
Source: Yanbu_Hotel_Design_Review_Checklist_v2_1.xlsx. Anchors identify the top-left Excel cell of each image. Images may span adjacent rows. Reference-project identities and original attributions were not supplied; these images are not presented as verified built works of the project team.

Source library

Sources, basis and use of this presentation.

A complete design narrative with direct access to its supporting evidence.

68 / 68

Project plans
R18 architectural and furniture layout set, 16 sheets WFY-AR-000 to 133 (9 November 2026); FLS and circulation plans R18; earlier solar, structural and schedule studies A-18–A-31 (September 2026).
Open drawing library · R18 downloads

Project quantities
R18 area schedule (WFY-AR-000); Proposed Facilities of Hotel and Annex – FINAL; Yanbu Hotel Space Program – FINAL; room matrix 228 keys / 305 modules.
Reconciliation and calculation downloads

Project review
RCJY Presentation Requirements Compliance Checklist: 27 items and 34 embedded images. Yanbu Hotel Design Review Checklist v2.1: 13 items, team remarks and 17 embedded images.
RCJY cross-reference · Design review close-out

Design imagery
16 exterior views (roof views updated to the latest PV and parapet design, November 2026) plus 6 latest R18 views; 44 supplied interior views in 22 pairs; Coordinated Interiors V2 guide; two material boards; coloured landscape plan.
Exterior collection · Interior collection

Forma evidence
Wafaiya Yanbu — Environmental Analysis, dated 19 September 2026. All 21 embedded figures preserved.
Forma evidence library

Wind analysis methodology
Autodesk describes rapid directional estimates and more detailed CFD-based studies, with activity-specific comfort scales.
Autodesk Forma wind analysis

Regional planting
Regional flora sources document relevant coastal and saline communities; final planting needs a project-specific horticultural assessment.
Northern Tihama flora · Sabkhas flora

Materials and coatings
Product contribution to LEED and coastal coating preparation need evidence for the actual products and assemblies.
USGBC product guidance · QUALICOAT Seaside

Regulatory references
Use the permit edition, project-specific RCJY criteria and hotel-classification criteria accepted by the reviewing authorities.
Saudi Building Code system · Ministry of Tourism published hotel checklist

Presentation basis: the supplied information and client corrections available on 29 September 2026. New diagrams explain design principles; they are not measured construction drawings. Numerical source differences, concept specifications and unverified technical outcomes are identified where they affect the presentation.
Prepared as an architectural design-development presentation. External references checked 29 September 2026. Use the controlled consultant issue for statutory submission and construction.

Presentation contents

The design

1A hotel shaped by the bay2One destination. Four connected strengths.3The bay is the organising idea.4The site model connects land, bay and horizon.5A repeated fold with a clear purpose.6A view strategy that supports the room offer.7Two arrivals, one coherent destination.8The annex broadens the destination.

Project numbers

9The project, measured transparently.10305 room modules across five guest floors.

Guest experience

11The view continues inside.12A connected offer for meetings and celebrations.13Wellness and outdoor life form one sequence.14A roof destination with an environmental response.

Climate response

15Keep the sheltered podium. Improve the exposed roof.16Moderate the wind while keeping the view open.17Shade the occupied areas. Reserve the solar opportunity.18Read the shadow through the day and the seasons.19Protect the outlook from heat and glare.

Landscape

20A coastal landscape carried above the basement.21Select for coastal ecology, then verify the planting system.

Materials

22Warm stone at the arrival.23A durable palette along the sea frontage.24Solid aluminium gives the bronze language precision.25A layered external wall for a coastal hotel.26Turn sustainability intent into documented performance.

Plans & architecture

27A clear hierarchy from operations to the roof.28Basement — the operating backbone.29Ground floor — arrivals, dining and large halls.30Mezzanine — wellness and administration.31First floor — meetings and multipurpose rooms.32Second floor — 61 room modules.33Third floor — the repeated guest module.34Fourth floor — continuity of the guest floors.35Fifth floor — the upper suite offer.36Sixth floor — the highest guestroom level.37Roof deck — hospitality, shelter and services.38Front and rear elevations.39Left and right elevations.40Sections reveal the spatial hierarchy.

Exterior collection

41The setting and the approach.42Arrival, connection and evening identity.43Water, balconies and the coastal outlook.44Life along the sea-facing terraces.45Latest views – roof PV and parapet.46Films and R18 downloads.

Interior collection

47Main lobby and reception & lobby cafe.48All-day dining & business lounge.49Banquet hall & conference room.50Corner meeting room & breakout meeting room.51Boardroom & fitness centre.52Basketball court & spa reception.53Spa treatment room & moroccan bath.54Guest corridor & lift lobby.55King bedroom & twin bedroom.56Suite living room & suite dining room.57Suite office & roof restaurant.

Submission & evidence

58Coordinate the systems that make the hotel work.59RCJY requirements — design and drawings.60RCJY requirements — visuals, systems and delivery.61Carry the review comments into design development.62A staged route from concept to a coordinated hotel.63One project needs one controlled set of numbers.

Source library

64The R18 drawing library.65The supplied environmental evidence.66Visual references embedded in the RCJY checklist.67Visual evidence embedded in the design review.68Sources, basis and use of this presentation.